Pipeline Construction

Winter Pipeline Project

Major Upstream E&P  |  Northwest, Alberta (Brintnell)  |  Winter 2009/2010

SCOPE OF WORK: 110km of various 4” -12” steel pipeline with 60kms of liner installation.

CHALLENGES/UNIQUENESS: Work performed during winter conditions with majority of ROW on muskeg. Applying proper coordination of a 200-man crew and 40 pieces of heavy equipment, the project was successfully completed on time.

TIME TO COMPLETE: 3.5 months