Facility Construction

Strainer Installation (N40 Strainers)

Large Integrated Midstream Company  |  Central Alberta (Edmonton, AB)  |  Winter 2016 - 2017

SCOPE OF WORK: Installed 2 x 24” 600# strainers and associated piping, performed field measurement verifications of existing facility piping, completed shop fabrication and hydro tests; 24”, 30” and 36” diameter spools, provided third-party coating of spooling, provided all logistics of materials and spools (fab shop, coating to site), and provided cranage to support the install.

CHALLENGES/UNIQUENESS: The work was performed on a live operating facility, hoisting and welding near live piping and electrical systems. The actual work area was extremely tight and congested, this required precision detailing due to the infrastructure.

TIME TO COMPLETE: 2.5 months

SUPPORTING DIVISIONS: Fabrication